November 12, 2026
When the railroad bridge over the St. Lucie River is down, its span sits 6.5 feet above mean high water, and boats taller than that wait. That clearance is why boats queue near the bridge. It is why the federal rail construction money awarded in August went to a bridge and not to a train station. It is also behind the main objection to putting that station at 500 SE Flagler Avenue. Rail projects in Stuart line up behind this bridge, and this year it moved to the front.
On August 18, 2026, USDOT awarded the City of Stuart a $78.9 million grant to replace the roughly 100-year-old St. Lucie River Railroad Bridge with a new double-track structure, according to Brightline's announcement of the award. The city was the applicant because the grant had to go to a public agency. A 2023 Martin County agenda item noted that neither Florida East Coast Railway nor Brightline is a public agency.
This year's award adds to an earlier one. TCPalm reported in December 2023 that the first federal grant was $130.5 million, when the project was estimated at $218 million. The estimate is now $262 million. Together the two awards come to about $209.4 million, which leaves roughly $53 million of the current estimate outside federal grants. The estimate rose by $44 million between the two awards, about half the size of the August grant.
The replacement is designed to change these dimensions:
| Measure | Current bridge | Planned replacement |
|---|---|---|
| Horizontal clearance | 50 feet | About 90 feet |
| Vertical clearance, closed, to mean high water | 6.5 feet | About 17.75 feet |
| Tracks | One | Two |
| Share of vessels that can pass with the bridge down | Not stated | More than 90 percent |
The 90 percent figure matters most for people on the water. The bridge will still close for trains, but most boats will be able to pass under it while it is down. It also matters on land, because the second track and lower maintenance costs are part of the project's case to the railroads using the corridor.
The bridge still runs on the operating schedule the Coast Guard set when its final rule took effect on November 17, 2025. The Coast Guard calls it the Florida East Coast Railroad Bridge, at mile 7.41 of the Okeechobee Waterway. Its announcement of the rule sets out this routine:
The proposed rule that led to this schedule cited a Coast Guard-commissioned study of 110 days of daytime traffic. It recorded 16,406 vessel transits. Of those, 5,325 boats had to wait, for an average of 20.2 minutes each. That works out to about one in three daytime passages stopped at the bridge. Comments on the same rule described recreational boats waiting 45 to 60 minutes after trains had cleared.
Local officials have described the problem bluntly. In Brightline's announcement, Congressman Brian Mast called the bridge "too low, sitting at 6 feet, too narrow, and stuck in the closed position more often than it should be." Michael Kennedy, Martin County's commissioner on the Florida Inland Navigation District, said in the same release that the new clearances "will substantially reduce impacts on recreational boaters, commercial marine traffic, downtown motorists, marine industries and cruising vessels."
The new bridge is still years away. TCPalm reported in May that the replacement may take until 2032 to finish. Until then, the 6 a.m. to 8 p.m. schedule above is how the bridge operates.
The Brightline station proposed for downtown Stuart runs into the same bridge. WQCS reported in June that Florida East Coast Railway, which owns the corridor, wrote to the city that it had blocked Brightline from moving ahead with the proposed station. Its reason was that trains stopping there would require the bridge to close every time a train arrived.
A station downtown would put a train stop right next to the river crossing, and a stopped train keeps the bridge down. This is why the June discussion at the Martin County Commission turned to location. According to WQCS, Commissioner Edward Ciampi asked county staff to talk with Brightline about the Martin County Fairgrounds property instead, since the fair is expected to move by 2028. He noted that the site sits between US-1 and the airport and could address the bridge concern. Commission Chair Sarah Heard said in the same report that the county has until June 30, 2027 to back out of the deal.
The downtown plan described by CBS12 in August is a 10,200-square-foot station on just over two acres at 500 SE Flagler Avenue, across from the Martin County Courthouse. The cost estimates have risen. TCPalm reported in February an $87 million project estimate. The same month, WPTV reported that the county had asked for just over $69.2 million in federal money. Its own contribution would be $15 million plus land assessed at $2.8 million.
The August federal round funded the bridge but not the station. WFLX reported that Martin County was not among the station recipients in that round. County officials told CBS12 afterward, "We still have an agreement with Brightline. We still have a proposed location, and we're still pursuing funding opportunities." The county's Brightline project page says funding and planning steps have to be completed before a lease and construction can begin. It also says that after two grant cycles, neither the county nor Brightline is required to build a station on the Treasure Coast.
Some downtown businesses want the station. Michelle Davis, who has owned Island Cotton Company in downtown Stuart for 17 years, told CBS12 that visitors "hopping off the trains to come and check out our downtown" would be "great for business." In September, TCPalm described renewed momentum for the station, and said time was running short.
The newest rail money in Stuart is for the street crossings, not the river. On November 5, the City of Stuart announced a $1.866 million award from the Federal Railroad Administration's Rail Crossing Elimination Grant Program. The program funded 91 grants in 37 states, and Stuart was the only Florida municipality selected. The city will pay the required 20 percent match.
The grant pays for planning at two crossings on the FEC mainline:
According to the city, the two crossings together had more than 200 crashes and safety-related incidents over the past five years. The study will rank possible safety improvements and assess whether a grade-separated crossing, which keeps trains and road traffic on different levels, is feasible. Mayor Eula Clarke said the work "will help position Stuart to compete for future construction funding." This follows the same order as the bridge. The bridge got a federal grant in 2023 and another in 2026. The crossings now have planning money, and construction money would come later.
The dates ahead, in order:
The bridge is the only one of the three projects with major construction funding in place. The station and the crossing work are both tied to the same rail line through downtown, and that line crosses the river 6.5 feet above the water. For more on how the rest of downtown is changing, see our look at downtown Stuart's fall calendar and the City Hall waterfront site and our Stuart and Treasure Coast neighborhood guide.
If you own a home on the St. Lucie River or near downtown Stuart and want to know how the bridge schedule and the crossing study could affect how you use your property and your plans for it, Holland Group can talk it through with you. Book a call with our team.
Some of our most recent posts.
We pride ourselves in providing personalized solutions that bring our clients closer to their dream properties and enhance their long-term wealth.